How to price an extra while a job is underway

You’re partway through painting a fence when the customer asks, “Can you do the gate too?” Before you pick up the brush, make it clear what the extra includes, how much it adds, and whether it changes the schedule.

Write down what changed

Keep the original fence scope visible. Add a separate description for the gate: for example, clean and paint both faces of one gate, excluding hardware repair. Check that the gate wasn’t already included in the fence measurement or price. Take a quick reference photo if it helps you confirm which gate the customer means.

Check the quantity and the price

Walk the extra work before pricing it. Check the surface condition, how many sides need painting, access, prep time and materials. If you use JobFlow to draft an estimate with AI, review the description, quantity and price against what you saw on site before sharing it.

Show the change before doing the work

For a fictional example, the agreed fence work is $480 and painting the gate adds $90. Show the original $480, the proposed $90 extra and the revised total of $570 if the customer agrees. Give the customer a chance to confirm the work, price and any revised finish date. Keep a dated copy of what they agreed to. Follow any change procedure already specified for the job.

Carry the same description into the invoice

If the gate is approved, use the same description and amount in the invoice. If the customer passes, leave the proposed extra off the invoice. Before sending, check that any payments already recorded are reflected in the remaining balance.

A quick check before you move on